Adams County LCC September 17 2024
- CDOT repairs on I-270 and Vasquez
- 9/16/24 – repairs begin both eastbound and westbound
- There will be overnight single lane closures – followed by 24/7 ramp closures
- In late September on-ramps will be closed for up to 4 days
- Both ramps will not be closed at the same time
- Project Schedule and Traffic Impacts can be found here
- Completion date is early October
- Weld county pilot program is successful
- 168 unduplicated riders
- They’ve added Milican
- Windsor is next focus
- This would then cover the entire Front Range
- Smaller towns are helping fund with things like local match while Weld County goes for the larger grant money, etc.